The final stages of dismantling the Old Waldo-Hancock Bridge are underway.The deck is completely gone and the cables now have to be removed.Ted talbot with the Department of Transportation says the main cable will be a 2 to 3 day process to dismantle, that should begin on Monday.After that, Talbot says the supplemental cables will be removed, that is expected to start on Thursday and will require closure of the Marine Channel.The coast guard is working with the department on that closure.Talbot says the majority of the bridge will be removed by the 24th.